Geary Boulevard Construction Starts in December: Bus Bulbs, Red Lanes and Trees Through Early 2028
Construction on the last phase of the Geary Boulevard Improvement Project starts in early December 2026 on Geary between Stanyan Street and 32nd Avenue in the Richmond District, the SFMTA said in a November 9 update. The work is expected to last through early 2028.
What Is Being Built
The SFMTA lists three main pieces of work for this phase:
- Bus bulbs and pedestrian bulbs, which extend the sidewalk at bus stops and crosswalks
- About 50 new street trees
- Red paint on the existing transit-only lanes
The changes serve the 38 Geary and 38R Geary Rapid buses. The project page puts the cost at $48 million and lists Presidio Heights, the Inner Richmond and the Outer Richmond as the affected neighborhoods. The project page describes the full project area as Geary between Stanyan Street and 34th Avenue.
How Construction Will Work
Crews will work mainly at intersections, and at several locations at the same time to shorten the overall schedule. The SFMTA says it will repave each segment once it is finished, so individual blocks see construction for a shorter stretch than they would if the whole corridor were dug up at once. Block-by-block drawings are linked from the project page.
This phase follows two earlier rounds of work. A quick-build phase, approved unanimously by the SFMTA Board on August 15, 2023 and installed that fall, added transit lanes, changed bus stops, adjusted transit signals and gave people walking more time to cross. Since then the San Francisco Public Utilities Commission has replaced sewer and water pipes and installed fiber optic conduit under the street. The first phase of work on the corridor, the Geary Rapid Project, was completed in fall 2021; this second phase extends it west into the Richmond.
Meetings and Business Support
The project team holds drop-in office hours on Tuesday, November 17, 2026, from 2pm to 5pm at Joe’s Ice Cream, 5420 Geary Blvd. Business owners and managers on the corridor can apply to join the Geary Small Business Working Group until Monday, November 30, 2026.
The SFMTA’s business support plan includes a merchant-directed campaign, ambassadors visiting the businesses closest to each bus bulb site before work starts, signs in active construction zones, emailed construction schedules, and social media and newspaper ads. Questions go to [email protected] or 415.646.2300, and updates are at SFMTA.com/Geary.
If You Ride or Drive Geary
Because the work moves between intersections, check the SFMTA’s construction updates at SFMTA.com/Geary before a trip on the corridor. Elsewhere on Geary, the T&T Supermarket at Geary and Masonic, east of the project area, opened on November 5.
Photo: Pi.1415926535, CC BY-SA 4.0, via Wikimedia Commons. The photo shows a temporary bus bulb at 20th Avenue in January 2021.
More SF News
San Francisco Will Merge Planning and Building Inspection Into One Department Under Prop FNov 20, 2026
Civic Center Plaza Tree Lighting Is December 2: Free, 4pm to 7pm, With the 50-Foot Fir Lit at 5:30pmNov 18, 2026
Muni Bus Cameras With AI Will Ticket Drivers Blocking Transit Lanes and Bus Stops Starting in 2027Nov 18, 2026
California DMV Bars Waymo From Freeways, So Robotaxi Rides to SFO Now Use Surface StreetsNov 18, 2026