California Awards $750 Million to The Portal, Caltrain’s Extension to the Salesforce Transit Center
California awarded $750 million on Tuesday, November 10, 2026, to The Portal, the planned two-mile extension of Caltrain from Fourth and King streets into the Salesforce Transit Center in downtown San Francisco. The money comes from the California State Transportation Agency’s Transit and Intercity Rail Capital Program and was the largest piece of nearly $1.3 billion in transit awards Governor Gavin Newsom announced the same day.
What the $750 Million Pays For
The award is multi-year funding, according to a statement from the Transbay Joint Powers Authority, the agency that owns and operates the Salesforce Transit Center and is leading the project:
- $100 million in this funding cycle goes to preconstruction work.
- $650 million is set aside for construction.
- The state money is meant to help leverage $3.38 billion the TJPA says is already committed through the Federal Transit Administration’s Capital Investment Grants program.
Urbanize SF, reporting on the award, put the project’s total cost at more than $7.5 billion. The governor’s office said the project is still advancing through the federal Capital Investment Grant process.
What The Portal Would Change for Riders
Caltrain’s San Francisco terminal today is at Fourth and King streets in SoMa. The Portal would run Caltrain trains in a tunnel into the train box already built beneath the Salesforce Transit Center, which the TJPA says would give riders direct connections to eight transit operators and put them one block from Embarcadero BART. The same station is planned as the San Francisco terminus for California high-speed rail, according to the governor’s office.
The TJPA projects an average of 90,000 daily riders once the extension is complete. “The Portal is San Francisco’s highest-priority transit expansion project,” TJPA Board Chair Jeff Gee and Executive Director Adam Van de Water said in their statement.
The award does not set an opening date, and neither the state nor the TJPA gave one with the announcement. The TJPA board’s next listed meeting is December 10, 2026.
Other Bay Area Awards in the Same Round
The governor’s office listed 28 awards statewide. Bay Area projects named in the announcement and in Urbanize SF’s coverage include:
- A second main track through Fremont and Newark for the Altamont Corridor Express (ACE).
- Caltrain’s battery-electric train pilot between San Jose and Gilroy, plus new track and safety infrastructure for Caltrain.
- $25 million for BART’s Ashby Station in Berkeley, where the west parking lot is planned to become 618 homes, 307 of them affordable.
- $40 million for Capitol Corridor to refurbish rail cars and add seating.
- $24.8 million for the Marin County Transit District, including 11 electric buses.
“From Caltrain’s extension into downtown San Francisco to clean buses in the Central Valley and tap-and-pay fares across Metrolink, these awards make transit cleaner, faster and easier for riders across the state,” said California Transportation Secretary Toks Omishakin.
If You’re Using the Transit Center Now
Nothing changes yet for riders. The Salesforce Transit Center remains a bus terminal with the rooftop Salesforce Park on top, and Caltrain trains continue to start and end at Fourth and King. The train box under the transit center has no train service until the extension is built.
Sources: Office of Governor Gavin Newsom, November 10, 2026; Transbay Joint Powers Authority statement on the TIRCP Cycle 8 award; Urbanize SF, November 11, 2026.
Photo: Sharon Hahn Darlin, CC BY 2.0, via Wikimedia Commons.
More SF News
San Francisco Will Merge Planning and Building Inspection Into One Department Under Prop FNov 20, 2026
Civic Center Plaza Tree Lighting Is December 2: Free, 4pm to 7pm, With the 50-Foot Fir Lit at 5:30pmNov 18, 2026
Muni Bus Cameras With AI Will Ticket Drivers Blocking Transit Lanes and Bus Stops Starting in 2027Nov 18, 2026
California DMV Bars Waymo From Freeways, So Robotaxi Rides to SFO Now Use Surface StreetsNov 18, 2026